Minutes of the meeting: Works Museum of Pont Aven

Information :

1- The construction of the museum will begin in July 2013 by the removal of asbestos. These operations do not require control over the site. Construction barriers will just affixed along the facade of the building on the sidewalk.

2- The schedule must meet the requirements of the client (CCA), namely : move quickly to open before July 2015.

3- The influence of the site on the site from September 2013 be validated as meeting with traders in September : a square occupied by trucks during the demolition phase and by the materials for the shell construction phase. This area will be closed from view by fences that will support communication.

4- Throughout the duration of the project, will be in the sens rue unique Lomenech (en amount).

5- If the schedule is respected structural work will be finished by July 2014, which would end the influence of the place. No summer would therefore a priori affected by this influence.

6- The demolition is part concentrated from September to mid-November 2013 : this is the piece that will bring more inconvenience : noise, at least dust and 2 blocked days for the installation of cranes (which 1 early September).

7- The parking lots were discussed : to encourage all construction workers to park in the parking lots of the Town Hall, it was discussed in the interest of putting parking in the blue zone over the street Lomenech.

8- The Steering Committee will meet in June about.

9- Recall of members of the Steering Committee, chaired by D. Doeuff, Deputy Mayor :

– Representatives of the client (CCA, town)

– Representatives of project management

– 2 Representatives of the Office of Tourism (staff or administrator)

Isabelle Chaillie (President) or managing director

Valérie Brient (Director) tourisme@pontaven.com

– 3 Representatives Group Commercial

Patrice Le Louet lesajoncsdor29@orange.fr

Guislain Ropers ghislainropers@yahoo.fr
Sophie Stenhouse lapartdesanges29@gmail.com

Accessors :

Eric Jubin jubin.lamande @ orange.fr

Jean-Marc Tanguy moulin.grand.poulguin @ orange.fr

Valérie Bodolec roz.aven @ orange.fr

Anyone else wishing to participate in the meetings may be proposed on this box every time a call is broadcast.

All information will pass through groupement-pontaven@orange.fr

Thank you to send notices of meetings of the Steering Committee to 7 addresses above mentioned.

Thank you to communicate ROW plans and traffic this address to send to all members.

For the commercial group

The Recording Secretary,

Jean-Marc Tanguy

 